Purpose
The purpose of this procedure is to provide a guideline for opening a Work Order for a capital project.
References
N/A
Responsibilities
Project Manager (PM): It is the responsibility of the PM to secure a Work Order for each project they are managing.
Administration Division (ADM): Work Order Unit of ADM is responsible for maintaining the Bureau’s Work Order records and files.
Systems Division (SYS): SYS is responsible for monthly downloads of time charges which also get input into the Uniform Project Reporting System (UPRS).
Procedure
The Work Order is the heart of the cost accounting system. It is one of the first items of business for a PM to secure for a prospective project. A work order is required for every project to be tracked in UPRS. The opening of a work order authorizes the tracking system to permit and collect time charges for the defined scope of work of a project. After the defined scope of work is completed, the closing of a work order prevents further charges against the work order.
A work order is utilized for three purposes: (1) a mechanism for tracking charges to a project; (2) a mechanism for the Bureau of Engineering (BOE) to collect payment for time charged on a project; and (3) a tool for assessing trends and collecting data to determine the amount of time required to perform a specific operation. This information can then be used to program staff time in the Work Program Resource Requirement (WPRR) for this function when it arises again. On occasion, more than one work order may need to be opened for a specific project to track the charges and bill the appropriate client but a single work order should never be used for more than one project.
The PM should open and establish a work order number when activities are requested and needed to fulfill a desired project outcome. Processing a work order allows a PM to collect costs for a particular scope of work or project in the BOE.
Work Orders can be grouped into two main categories:
Capital Improvement Projects
Reimbursable Projects
Capital Improvement Projects are the budgeted projects that have received prior authority as part of a BOE program, whether it is Streets, Stormwater, Wastewater, a State Proposition, Bond Program or Grant Program.
A reimbursable project is when an owner/client department or agency is responsible for reimbursing the BOE for the agreed upon charges incurred by the BOE on this project. These projects are usually defined by a mutual agreement between an owner/client department or agency and the BOE. Examples of these projects are Memorandum of Understanding (MOU) or General Accounting Inter-Departmental Order (GAEID) funded projects, investigations or remediation requested by the City Attorney’s Office, and Interagency Agreements. In order to justify opening a Reimbursable Project Work Order, a written document such as an MOU or an GAEID from an owner/client department or agency should be submitted along with the appropriate form to the Work Order Unit of the ADM. The head of ADM can grant exceptions to this rule.
Form ENG 3.35 (Attachment 3.2-1) is to be used for all projects. The form should be filled out completely, signed by the Project and Division/Group Managers and sent to the Work Order Unit of the ADM. When the work order is authorized, photocopies are distributed to the appropriate offices.