11.1 Introduction

Revised on 02-26-2025

PURPOSE

The purpose of this procedure is to help the Project Manager or Project Engineer obtain the necessary permits and approvals in a timely manner so as not to delay the project.

REFERENCES

N/A

RESPONSIBILITIES

  • Project Manager (PM): It is the PM’s responsibility to ensure that the required applications and approvals necessary to complete his or her project are obtained within the correct scheduled timeframe.

  • Project Engineer (PE): On large or complex projects the PM may bring in a Project Engineer to assist the PM with his/her responsibilities. It is the PE’s responsibility to investigate, prepare, file, and obtain the required applications and approvals necessary to complete his or her design.

  • Contractor: After the contract is awarded, it may be the Contractor’s responsibility to pay for and obtain the permits necessary to construct the project (as determined by the contract language).

PROCEDURE

All projects require environmental clearance, and most projects require permits and approvals from regulatory agencies that must be obtained before the project can be constructed. Environmental clearance, Building & Safety permits, Cultural Affairs approval, California Coast Commission, South Coast Air Quality Management District (SCAQMD), Los Angeles Regional Water Quality Control Board (RWQCB), and various other regulatory agency approvals are just some of the permits and approvals that may be required depending on the project. Utility coordination is not technically an approval, but it must be completed prior to the start of construction. It is addressed in Chapter 8 of this manual.

The following is a list of permits that may be required. This list is not exhaustive, and not all of the permits listed would be required of every job.

PermitApproval/Issuing Authority
Environmental ClearanceBuilding & Safety
Building PermitBuilding & Safety
Grading PermitBuilding & Safety
Plumbing PermitBuilding & Safety
Electrical PermitBuilding & Safety
Structural PermitBuilding & Safety
Mechanical PermitBuilding & Safety
Demolition PermitBuilding & Safety
Elevator Permit and Plan CheckBuilding & Safety
Underground TanksFire Department
A PermitPublic Works, Bureau of Engineering
B PermitPublic Works, Bureau of Engineering
Sewer PermitPublic Works, Bureau of Engineering
Excavation PermitPublic Works, Bureau of Engineering
Utilities PermitPublic Works, Bureau of Engineering
Peak Hour ExemptionPublic Works, Bureau of Engineering
Industrial Waste Discharge PermitPublic Works, Bureau of Sanitation
Permits for Closure of Streets, Alleys, or SidewalksPublic Works, Bureau of Street Services
Tree Removal PermitPublic Works, Bureau of Street Services
Overload PermitPublic Works, Bureau of Street Services
Night and Weekend WorkLos Angeles Police Department
Noise VarianceLos Angeles Police Department
Coastal Commission PermitCoastal Commission
Air Quality Management District (AQMD) Permit to ConstructSCAQMD
AQMD Permit to OperateSCAQMD
Conditional Use PermitPlanning Department
Cultural AffairsCultural Affairs
Haul Route PermitPublic Works, Bureau of Street Services
Fire PermitFire Department
Industrial SafetyPublic Works, Bureau of Sanitation
Traffic Control PlanDOT
National Pollutant Discharge Elimination System (NPDES) PermitRWQCB
Stormwater Discharge PermitRWQCB